Q: 36 Men can complete a piece of work in 18 days. In how many days will 27 men be able to complete the same work?
A. 29 1/5 B. 37 1/4
C. 42 D. 24

Answer and Explanation

Answer:24

Explanation:
Let the required number of days be x
Then, less men, more days (indirect proportion)
Hence, 27 : 36 :: 18 : x
=> 27 * x = 36 * 18
=> x = 24