Home > Arithmetic Aptitude > Time and Work > Questions and Answers Discussion
Q: | P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work? | ||||||||||
|