Q: If 6 men working together can complete 50 identical tasks in 4 hours then how many such identical tasks can be completed if 10 men are working together for 6 hours?
A. 20 B. 125
C. 100 D. 60

Answer and Explanation

Answer:125

Explanation:
M1*D1*W2 = M2*D2*W1
Where, M – number of people working
D – time of work
W – number of tasks or work
6*4*W2 = 10*6*50
W2 = 125 tasks