Q: A can complete 1/3rd of a piece of work in 4 days and B can complete 1/6th of the same work in 3 days. In how many days will A and B can complete the same work, working together?
A. 6 1/3 B. 8
C. 7 1/5 D. 7

Answer and Explanation

Answer:7 1/5

Explanation:
A’s 4 day’s work = 1/3
A’s 1 day’s work = 1/12
B’s 3 day’s work 1/6
B’s 1 day’s work = 1/18
(A+B)’s 1 day work = 1/12 + 1/18 = 5/36
A and B together will complete the work in 36/6 days
= 7.2 days